FEATURED AUSTRALIA QLD BUSINESS REPORT: At $31 billion, is Inland Rail the most significant waste of public money in history?

Published on

in

@acenewsservices

This is our daily post that is shared across Twitter & Telegram and published first on here with Kindness & Love XX on peace-truth.com/

#AceNewsRoom in Kindness & Wisdom provides News & Views @acenewsservices

Ace Press News From Cutting Room Floor: Published: Apr.06: 2023:

#AceBusinessDesk – The cost of Australia’s largest rail project has doubled to an “astonishing” $31.4 billion and is riddled with problems such as major delays, environmental challenges and inexperienced project managers.

(AAP Image/Dan Peled)

Farmers and rural residents from the Darling Downs region protested outside the Commonwealth offices in Brisbane last year.

An independent review into the Inland Rail, which links Melbourne and Brisbane to take freight off roads, has found the project faces “serious problems” and some work should stop to get costs under control.

Report author Dr Kerry Schott said construction began “somewhat surprisingly”, without knowing where the route would start or finish.

“The detailed and clearly defined scope of much of the route has not yet been settled as approval processes are not complete,” Schott wrote in the report, due to be made public on Thursday morning.

“Until this scope is firmed, an assessment of schedule and cost cannot be made with confidence.”

A freight line from Melbourne to Parkes will take priority in an overhaul of the Inland Rail project, after an independent study found a massive cost blowout under the coalition government.

Inland Rail is a 1700km line intended to link Melbourne and Brisbane via regional Victoria, NSW and Queensland.

When finished it is expected to reduce truck volumes across at least 20 regional towns, ease congestion on major highways, cut carbon emissions and provide a reliable network for producers, farmers and businesses.

A study released on Thursday has found the project, estimated to cost $9.3 billion five years ago, has blown out to $31.4 billion.

Report author Kerry Schott said the section between Melbourne and Parkes could be completed by 2027, but there was no indication of the timing of the project beyond this.

Dr Schott said while progress was being made in terms of NSW approval processes, Queensland’s work was “well behind”.

She would not “hang her hat” on the 2030s estimate for the Queensland leg of the project.

Transport Minister Catherine King said it would take a lot of work to get the project back on track.

“The previous government began this project with no idea where the rail line would start in Melbourne, and where it would finish in Brisbane, or how it would interact with towns, communities and the natural environmental along the route,” she said.

Dr Schott found the government-owned Australian Rail Track Corporation did not have the expertise to manage the project, recommending Inland Rail be made a subsidiary company to allow it greater control of project management and approvals processes.

But the academic and Albanese government insist the project should go ahead.

“As it stands, Inland Rail is expected to accommodate and drive a modal shift of 200,000 trucks a year to rail, and this will bring significant benefits in terms of supply chain efficiencies, safety, environmental and congestion reductions,” Dr Schott said.

Ms King said the government had accepted in principle or in full all of Dr Schott’s recommendations, which would lead to “sweeping changes” to the project.

An independent cost estimator and value engineer will be appointed to undertake detailed assurance work.

Experts would also be added to the ARTC, with recruitment under way for an Inland Rail CEO.

“Inland Rail does remain an important project to meet Australia’s growing freight task, improve road safety and to help decarbonise our economy, but we have been left with one almighty mess,” the minister said.

Finance Minister Katy Gallagher, who is a shareholder minister in the project, said it would take 18 months to work through detailed costings.

About $2 billion has been spent so far.

In QLD Report: Published Thursday April 06, 2023
@acenewsservices

Editor says …Sterling Publishing & Media Service Agency is not responsible for the content of external site or from any reports, posts or links, and can also be found here on Telegram: https://t.me/acenewsdaily and thanks for following as always appreciate every like, reblog or retweet and comment thank you

@acenewsservices

Hey!

Hey there, fellow Robloxian! Whether you’re here to discover hidden gem games, level up your building skills, or just stay in the loop with the latest events, you’re in the right place. This blog is all about sharing the coolest things in the Roblox universe—from developer tips to epic game reviews. So grab your Bloxy Cola, hit that follow button, and let’s explore the world of Roblox together! 🚀


Join the Club

Stay updated with our latest tips and other news by joining our newsletter.

Discover more from Peace & Truth

Subscribe now to keep reading and get access to the full archive.

Continue reading

Discover more from Peace & Truth

Subscribe now to keep reading and get access to the full archive.

Continue reading